The gate-to-dock workflow for logistics parks
Short answer: a truck visit has five steps, appointment, identity check, gate entry, dock operation and exit. The park usually owns the gate and shared roads, the tenant owns the dock and its warehouse system. Measure dwell time from gate in to gate out and report the median (p50) and the 90th percentile (p90), not the average.
Who owns which step
Confusion between park operator and tenant causes most queues. Write down ownership for each step and the hand-off between them.
Measuring dwell time with p50 and p90
Record a timestamp at gate in, dock assigned, dock start, dock end and gate out. Dwell is gate out minus gate in. The p50 shows a typical visit; the p90 shows the slow tail that drivers and carriers complain about. Averages hide that tail.
Example: for ten visits of 22, 25, 28, 30, 31, 33, 35, 40, 55 and 90 minutes, the p50 is about 32 minutes and the p90 about 55 minutes, while the average of 38.9 minutes describes almost no real visit.
Exceptions to design for
Each exception needs an owner and a default action.
- Truck without an appointment: hold in a buffer area, tenant confirms or rejects
- Plate not recognised or driver ID mismatch: manual check by security with a logged reason
- Dock not ready: truck waits in the buffer, not on the access road
- Seal or document problem at the dock: tenant decision, park only informed
- Overstay in the yard: alert to the tenant after an agreed threshold
Gate-to-dock steps
| Step | Usual owner | Data captured | Common exception |
|---|---|---|---|
| Appointment | Tenant or carrier | Slot, carrier, plate, load | No appointment |
| Identity | Park security | Driver ID, plate read | Mismatch or unread plate |
| Gate in | Park operator | Timestamp, barrier event | Queue on public road |
| Dock | Tenant | Dock assigned, start and end | Dock not ready |
| Exit | Park operator | Timestamp, barrier event | Overstay |
Rollout checklist
- Agree step ownership between park and each tenant
- Confirm barrier and plate recognition events can be logged
- Define buffer area rules
- Choose dwell thresholds for alerts
- Report p50 and p90 weekly per tenant
Notes
Yard and dock scheduling inside a tenant's warehouse remains in the tenant's WMS or TMS. Hardware integrations are scoped per park after a technical audit.
FAQ
Why use p90 instead of average dwell time?
The average hides the slow visits that cause queues and carrier complaints. The p90 shows the time within which nine in ten visits finish.
Who is responsible for trucks waiting at a logistics park?
The park operator usually owns the gate, roads and buffer areas; the tenant owns the dock. The rules should say who acts at each step.
What happens when a truck arrives without an appointment?
It waits in a buffer area while the tenant confirms or rejects it, so the access road stays clear.
Request a walkthrough
Tell us about your portfolio and we will run this workflow on a property like yours. Write to office@realtynno.com.
Request a walkthrough